LOCATION
Hershey, Pennsylvania
CLIENT
The Pennsylvania State University
PROJECT DETAILS
- Substation Modification
- 69 kV Switchgear
To accommodate the needs of the new 7.9 MW CHP plant, BC Energy made substation modifications. The modification is specifically for the 69 kV Switchgear including two 69 kV PT units (foundation, grounding, H-Frames, and control conduits) and provided new current transformers and breakers for both utility feeds.