LOCATION
Worcester, Massachusetts
CLIENT
UMass Memorial Medical Center
PROJECT DETAILS
- 350 Ton Absorption Chiller
Alongside the design-build construction of a combined heat and power system, BC Energy installed a 350-ton absorption chiller into UMMC’s existing physical plant. To retrofit the already crowded plant to accommodate the large equipment, BC Energy personnel utilized 3-D laser scanning technology to determine where the unit could be located and how to physically move the equipment into the plant. The new chiller (capable of cooling 1.3 M Ton-hours annually) provides additional air conditioning to the hospital and enhances the critical utility infrastructure.